DETAIL PROGRESS KNMP

90
Lokasi Progress Bergerak
18.11%
Progress Nasional
0.19%
Rata-rata per Site
0
Site Selesai 100%
TREND PROGRESS NASIONAL
TOP KENAIKAN PROGRESS
Takkalasi SULAWESI SELATAN
+50%
Mattiro Bombang SULAWESI SELATAN
+46%
Tamarupa SULAWESI SELATAN
+44%
Pajjukukang SULAWESI SELATAN
+43%
Borimasunggu SULAWESI SELATAN
+42%
Bassiang Timur SULAWESI SELATAN
+39%
Lasama SULAWESI TENGGARA
+39%
Latawe SULAWESI TENGGARA
+38%
Lero Pinrang SULAWESI SELATAN
+36%
Bone Pute SULAWESI SELATAN
+36%
Tadang Palie SULAWESI SELATAN
+33%
Lakara SULAWESI TENGGARA
+32%
Karang-karangan SULAWESI SELATAN
+32%
Tondasi SULAWESI TENGGARA
+31%
Tanjung Laimeo SULAWESI TENGGARA
+31%
RANKING PROVINSI
Provinsi Total Site Avg Completion Hub Penyangga
SULAWESI TENGGARA 15 23.73% 4 11
SULAWESI SELATAN 50 20.26% 7 43
SULAWESI BARAT 6 15.83% 0 6
SULAWESI TENGAH 14 15.36% 2 12
GORONTALO 11 5.45% 1 10
TOP 10 PROVINSI
ProvinsiAvg Completion
SULAWESI TENGGARA 23.73%
SULAWESI SELATAN 20.26%
SULAWESI BARAT 15.83%
SULAWESI TENGAH 15.36%
GORONTALO 5.45%
DISTRIBUSI PROGRESS NASIONAL
0%
11
1-25%
58
26-50%
27
51-75%
0
76-99%
0
100%
0
PROGRESS TERBARU
Dusunan
SULAWESI TENGAH

17% Land Clearing & Levelling Lahan
Land Clearing & Levelling Lahan
2026-08-31 10:56:00
Boyantongo
SULAWESI TENGAH

18% Pekerjaan Pembesian dan Land Clearing

2026-08-31 10:53:00
Pajjukukang
SULAWESI SELATAN

24% Pekerjaan DPT, Saluran dan Pabrik Es Portable
* Pengecoran DPT * Pemasangan batu galian saluran * Galian tanah pabrik es portable
2026-08-31 10:33:00
Borimasunggu
SULAWESI SELATAN

35% Pek. Pabrik Es Portable dan DPT
* Pek. Pembesian Dinding Penahan Tanah * Pek. Galian Pabrik Es Portable
2026-08-31 10:30:00
Sausu Tambu
SULAWESI TENGAH

10% Leveling Lahan
Leveling Lahan
2026-08-31 10:15:00
Pelawa Baru
SULAWESI TENGAH

15% Leveling Lahan
Leveling Lahan
2026-08-31 10:15:00
Dusunan
SULAWESI TENGAH

17% Leveling Lahan
Leveling Lahan
2026-08-31 10:14:00
Laemanta Utara
SULAWESI TENGAH

11% Leveling Lahan
Leveling Lahan
2026-08-31 10:14:00
Watolo
SULAWESI TENGGARA

7% Pekerjaan Pondasi Tapak
* Pemasangan Cerucuk Dolken * Fabrikasi Pembesian
2026-08-30 17:14:00
Tubo Poang
SULAWESI BARAT

2% Land Clearing
* Land Clearing
2026-08-30 10:16:00
DETAIL SITE
Site Provinsi Status Completion Updated
SITE00132
Taula'a
GORONTALO PENYANGGA 0% 2026-08-19 11:42:36 Lihat Site
SITE00151
Sumpang Binangae
SULAWESI SELATAN PENYANGGA 0% 2026-08-13 12:41:59 Lihat Site
SITE00106
Muara Bone
GORONTALO PENYANGGA 0% 2026-08-19 11:33:38 Lihat Site
SITE00144
Tanjung Pinang
SULAWESI TENGGARA PENYANGGA 0% 2026-08-13 12:44:05 Lihat Site
SITE00146
Sama Bahari
SULAWESI TENGAH PENYANGGA 0% 2026-09-09 09:58:56 Lihat Site
SITE00133
Deme Ii
GORONTALO PENYANGGA 0% 2026-08-19 11:21:45 Lihat Site