DETAIL PROGRESS KNMP

100
Lokasi Progress Bergerak
41.55%
Progress Nasional
0.37%
Rata-rata per Site
0
Site Selesai 100%
TREND PROGRESS NASIONAL
TOP KENAIKAN PROGRESS
Mattiro Bombang SULAWESI SELATAN
+79%
Lero Pinrang SULAWESI SELATAN
+75%
Limbua SULAWESI BARAT
+70%
Tadang Palie SULAWESI SELATAN
+69%
Punagaya SULAWESI SELATAN
+69%
Terapung SULAWESI TENGGARA
+68%
Tamarupa SULAWESI SELATAN
+67%
Lumpue SULAWESI SELATAN
+66%
Bontorannu SULAWESI SELATAN
+65%
Takkalasi SULAWESI SELATAN
+65%
Data SULAWESI SELATAN
+70%
Arungkeke Pallantikang SULAWESI SELATAN
+64%
Watolo SULAWESI TENGGARA
+65%
Bungeng SULAWESI SELATAN
+63%
Lasama SULAWESI TENGGARA
+63%
RANKING PROVINSI
Provinsi Total Site Avg Completion Hub Penyangga
SULAWESI TENGGARA 15 52.33% 4 11
SULAWESI SELATAN 50 50.54% 7 43
SULAWESI BARAT 6 45.33% 0 6
SULAWESI TENGAH 14 44.50% 2 12
GORONTALO 11 36.09% 1 10
SULAWESI UTARA 15 0.53% 3 12
TOP 10 PROVINSI
ProvinsiAvg Completion
SULAWESI TENGGARA 52.33%
SULAWESI SELATAN 50.54%
SULAWESI BARAT 45.33%
SULAWESI TENGAH 44.50%
GORONTALO 36.09%
SULAWESI UTARA 0.53%
DISTRIBUSI PROGRESS NASIONAL
0%
11
1-25%
12
26-50%
42
51-75%
45
76-99%
1
100%
0
PROGRESS TERBARU
Tadang Palie
SULAWESI SELATAN

11% Pekerjaan Besi dan Pondasi
* Pek. Perakitan Besi dan Penimbunan area lokasi * Pemasangan cerucut kayu dolken * Pemasangan Pondasi saluran * Fabrikasi Pembesian
2026-08-04 10:50:00
Pallameang
SULAWESI SELATAN

3% Pek. Perakitan besi, dan Penimbunan area lokasi
Pek. Perakitan besi, dan Penimbunan area lokasi
2026-08-04 10:48:00
Lero Pinrang
SULAWESI SELATAN

4% Pekerjaan Sondir, Besi dan Penimbunan
* Pekerjaan Sondir tanah lokasi * Perakitan Besi dan Penimbunan Area Lokasi * Fabrikasi Pembesian
2026-08-04 10:46:00
Bassiang Timur
SULAWESI SELATAN

2% Leveling Lahan dan Sondir
Pekerjaan Leveling Lahan dan Sondir
2026-08-03 11:08:00
Padang Kalua
SULAWESI SELATAN

1% Mobilisasi Materials
Mobilisasi Materials
2026-08-03 11:06:00
Tirowali
SULAWESI SELATAN

3% Pemagaran
Pekerjaan pemagaran lokasi proyek
2026-08-03 11:04:00
Bone Pute
SULAWESI SELATAN

3% Lanjutan Leveling Lahan
Pekerjaan Penimbunan
2026-08-03 11:00:00
Bulete
SULAWESI SELATAN

1% Mobilisasi Materials
Mobilisasi Materials
2026-08-03 10:55:00
Karang-karangan
SULAWESI SELATAN

2% Pekerjaan Pembesian
Pekerjaan Pembesian
2026-08-03 10:47:00
Mattiro Bombang
SULAWESI SELATAN

14% Pekerjaan Revetment, Penahan Tanah, Cold Storage dan Kios perbekalan
Pekerjaan galian tanah pondasi tapak Revetment Pekerjaan pembesian besi beton pondasi tapak Revetment Pekerjaan cerucuk kayu dolken turap beton dinding penahan tanah Pekerjaan pemasangan bekesting pondasi dinding penahan tanah Pekerjaan pembesian dinding beton t = 20 cm dinding penahan tanah Pekerjaan Pegecoran beton dinding penahan tanah Pekerjaan pengecoran sloof bangunan shelter pendaratan ikan Pekerjaan pemadatan tanah urug bangunan pabrik es portable Pekerjaan pengecoran kolom beton pedestal bangunan kios perbekalan
2026-08-03 10:29:00
DETAIL SITE
Site Provinsi Status Completion Updated
SITE00085
Moilong
SULAWESI TENGAH PENYANGGA 24% 2026-11-04 11:08:40 Lihat Site
SITE00127
Huwongo
GORONTALO PENYANGGA 23% 2026-11-09 14:43:59 Lihat Site
SITE00106
Muara Bone
GORONTALO PENYANGGA 18% 2026-11-12 10:39:31 Lihat Site
SITE00111
Olimoo'O
GORONTALO PENYANGGA 17% 2026-11-09 14:42:16 Lihat Site
SITE00145
Lero Donggala
SULAWESI TENGAH PENYANGGA 17% 2026-11-25 09:56:03 Lihat Site
SITE00114
Biluhu Tengah
GORONTALO PENYANGGA 15% 2026-10-20 11:59:38 Lihat Site
SITE00180
Naha 1
SULAWESI UTARA PENYANGGA 3% 2026-11-12 11:13:45 Lihat Site
SITE00181
Gangga 2
SULAWESI UTARA PENYANGGA 2% 2026-10-30 13:11:17 Lihat Site
SITE00179
Kahuhu
SULAWESI UTARA PENYANGGA 2% 2026-11-12 11:18:13 Lihat Site
SITE00182
Lamanggo
SULAWESI UTARA HUB 1% 2026-10-29 13:21:33 Lihat Site