← Kembali ke Peta

DETAIL PROGRESS KNMP

100
Lokasi Progress Bergerak
42.03%
Progress Nasional
0.38%
Rata-rata per Site
0
Site Selesai 100%
TREND PROGRESS NASIONAL
TOP KENAIKAN PROGRESS
Mattiro Bombang SULAWESI SELATAN
+79%
Lero Pinrang SULAWESI SELATAN
+75%
Limbua SULAWESI BARAT
+70%
Tadang Palie SULAWESI SELATAN
+69%
Punagaya SULAWESI SELATAN
+69%
Borimasunggu SULAWESI SELATAN
+69%
Terapung SULAWESI TENGGARA
+68%
Tamarupa SULAWESI SELATAN
+67%
Lumpue SULAWESI SELATAN
+66%
Bontorannu SULAWESI SELATAN
+65%
Takkalasi SULAWESI SELATAN
+65%
Data SULAWESI SELATAN
+70%
Arungkeke Pallantikang SULAWESI SELATAN
+64%
Watolo SULAWESI TENGGARA
+65%
Bungeng SULAWESI SELATAN
+63%
RANKING PROVINSI
Provinsi Total Site Avg Completion Hub Penyangga
SULAWESI TENGGARA 15 53.53% 4 11
SULAWESI SELATAN 50 51.24% 7 43
SULAWESI BARAT 6 45.33% 0 6
SULAWESI TENGAH 14 44.50% 2 12
GORONTALO 11 36.09% 1 10
SULAWESI UTARA 15 0.53% 3 12
TOP 10 PROVINSI
ProvinsiAvg Completion
SULAWESI TENGGARA 53.53%
SULAWESI SELATAN 51.24%
SULAWESI BARAT 45.33%
SULAWESI TENGAH 44.50%
GORONTALO 36.09%
SULAWESI UTARA 0.53%
DISTRIBUSI PROGRESS NASIONAL
0%
11
1-25%
12
26-50%
41
51-75%
46
76-99%
1
100%
0
PROGRESS TERBARU
Pabiringa
SULAWESI SELATAN

1% Pemagaran & Stakeout

2026-08-06 10:44:00
Songka
SULAWESI SELATAN

3% Leveling Lahan, Pengukuran & Pekerjaan Besi
Leveling Lahan, Pengukuran & Pekerjaan Besi
2026-08-06 10:34:00
Takkalasi
SULAWESI SELATAN

2% Fabrikasi Pembesian
*Fabrikasi Pembesian Note: Untuk Sementara waktu permbersihan area kerja belum bisa di lakukan dikarenakan terkendala pembebasan lahan, dan area yang akan dibangun masih terdapat rumah warga, di rencanakan tanggal 10 Agustus akan dilakukan pembongkaran jika berjalan lancar.
2026-08-06 10:10:00
Tondasi
SULAWESI TENGGARA

5% Penerimaan Material & Pematokan Batas Area
* Penerimaan Pasir * Penerimaan Batu Gunung * Pemagaran Area Kerja
2026-08-06 09:44:00
Tirowali
SULAWESI SELATAN

9% Pematokan Untuk Galian Pondasi

2026-08-06 09:02:00
Boyantongo
SULAWESI TENGAH

1% Pemagaran & Mobilisasi Material
Pemagaran & Mobilisasi Material
2026-08-05 16:42:00
Tondasi
SULAWESI TENGGARA

1% Pekerjaan Persiapan
Pekerjaan Persiapan
2026-08-05 12:39:00
Pallameang
SULAWESI SELATAN

6% Perakitan besi dan Pekerjaan Galian
* Pek. Perakitan besi * Pek. Galian Dpt dan Saluran
2026-08-05 11:45:00
Lero Pinrang
SULAWESI SELATAN

9% Pekerjaan Pembangunan Kios Perbekalan
* Pek. Perakitan Besi * Pemasangan Pondasi batu kali kios perbekalan * Fabrikasi Pembesian
2026-08-05 11:37:00
Munte
SULAWESI SELATAN

1% Survey Lokasi
Survey Lokasi Desa Munte
2026-08-05 11:24:00
DETAIL SITE
Site Provinsi Status Completion Updated
SITE00124
Kasia
GORONTALO PENYANGGA 67% 2026-11-25 10:50:19 Lihat Site
SITE00084
Lumpue
SULAWESI SELATAN PENYANGGA 66% 2026-11-24 09:36:48 Lihat Site
SITE00073
Pelawa Baru
SULAWESI TENGAH PENYANGGA 66% 2026-11-25 09:37:36 Lihat Site
SITE00015
Bontorannu
SULAWESI SELATAN PENYANGGA 65% 2026-11-25 12:50:01 Lihat Site
SITE00013
Takkalasi
SULAWESI SELATAN PENYANGGA 65% 2026-11-24 11:39:28 Lihat Site
SITE00136
Watolo
SULAWESI TENGGARA PENYANGGA 65% 2026-11-25 09:15:01 Lihat Site
SITE00154
Arungkeke Pallantikang
SULAWESI SELATAN PENYANGGA 64% 2026-11-25 12:52:23 Lihat Site
SITE00026
Lasama
SULAWESI TENGGARA PENYANGGA 63% 2026-11-12 10:34:44 Lihat Site
SITE00018
Bungeng
SULAWESI SELATAN PENYANGGA 63% 2026-11-25 12:53:26 Lihat Site
SITE00045
Burau Pantai
SULAWESI SELATAN PENYANGGA 60% 2026-11-19 15:59:06 Lihat Site