DETAIL PROGRESS KNMP

100
Lokasi Progress Bergerak
41.55%
Progress Nasional
0.37%
Rata-rata per Site
0
Site Selesai 100%
TREND PROGRESS NASIONAL
TOP KENAIKAN PROGRESS
Mattiro Bombang SULAWESI SELATAN
+79%
Lero Pinrang SULAWESI SELATAN
+75%
Limbua SULAWESI BARAT
+70%
Punagaya SULAWESI SELATAN
+69%
Tadang Palie SULAWESI SELATAN
+69%
Terapung SULAWESI TENGGARA
+68%
Tamarupa SULAWESI SELATAN
+67%
Lumpue SULAWESI SELATAN
+66%
Bontorannu SULAWESI SELATAN
+65%
Arungkeke Pallantikang SULAWESI SELATAN
+64%
Watolo SULAWESI TENGGARA
+65%
Takkalasi SULAWESI SELATAN
+65%
Data SULAWESI SELATAN
+70%
Lasama SULAWESI TENGGARA
+63%
Bungeng SULAWESI SELATAN
+63%
RANKING PROVINSI
Provinsi Total Site Avg Completion Hub Penyangga
SULAWESI TENGGARA 15 52.33% 4 11
SULAWESI SELATAN 50 50.54% 7 43
SULAWESI BARAT 6 45.33% 0 6
SULAWESI TENGAH 14 44.50% 2 12
GORONTALO 11 36.09% 1 10
SULAWESI UTARA 15 0.53% 3 12
TOP 10 PROVINSI
ProvinsiAvg Completion
SULAWESI TENGGARA 52.33%
SULAWESI SELATAN 50.54%
SULAWESI BARAT 45.33%
SULAWESI TENGAH 44.50%
GORONTALO 36.09%
SULAWESI UTARA 0.53%
DISTRIBUSI PROGRESS NASIONAL
0%
11
1-25%
12
26-50%
42
51-75%
45
76-99%
1
100%
0
PROGRESS TERBARU
Polewali
SULAWESI TENGGARA

46% Pekerjaan Shelter Pendaratan Ikan, Pabrik Es Portable, Kantor Pengelola dan Tambatan Perahu
= pek. Selther pendaratan ikan = pek. Pabrik es = pek. Kantor pengelola = pek. Dacking kapal = pek. Tulangan plat dan balok tambatan perahu
2026-11-12 17:25:00
Muara Sampara
SULAWESI TENGGARA

58% Pekerjaan Revetment
Pek. Pemasangan batu revetment
2026-11-12 17:19:00
Bone Pute
SULAWESI SELATAN

58% Pekerjaan Revetment dan Lantai Kerja

2026-11-12 16:39:00
Murante
SULAWESI SELATAN

43% Pekerjaan Kios Perbekalan dan Lantai Kerja

2026-11-12 15:33:00
Burau Pantai
SULAWESI SELATAN

57% Pekerjaan Revetment, Shelter Pendaratan

2026-11-12 11:26:00
Benteng
SULAWESI SELATAN

43% Pekerjaan Revetment dan DPT
•pengecoran revetment •pek.pembesian dpt
2026-11-12 11:07:00
Tondasi
SULAWESI TENGGARA

55% Pek DPT dan Revetment

2026-11-12 10:35:00
Siddo
SULAWESI SELATAN

32% Pekerjaan Pabrik Es Portable
* Pemasangan Bekisting Balok Bawah Bangunan Pabrik Es Portabel * Pengecoran Balok Bawah Bangun Pabrik Es Portabel
2026-11-11 19:54:00
Mabonta
SULAWESI SELATAN

52% Pekerjaan revetment
* Pek. Tangga revetmen * Pemasangan paving blok
2026-11-11 19:44:00
Muara Tinobu
SULAWESI TENGGARA

21% Pekerjaan dinding penahan tanah

2026-11-11 19:39:00
DETAIL SITE
Site Provinsi Status Completion Updated
SITE00060
Harapan
SULAWESI SELATAN PENYANGGA 55% 2026-11-24 09:42:01 Lihat Site
SITE00052
Polewali
SULAWESI TENGGARA HUB 55% 2026-11-25 10:01:29 Lihat Site
SITE00031
Tondasi
SULAWESI TENGGARA PENYANGGA 55% 2026-11-12 10:35:19 Lihat Site
SITE00079
Laemanta Utara
SULAWESI TENGAH PENYANGGA 55% 2026-11-18 10:18:44 Lihat Site
SITE00156
Rantebelu
SULAWESI SELATAN PENYANGGA 54% 2026-11-24 10:28:43 Lihat Site
SITE00044
Mabonta
SULAWESI SELATAN PENYANGGA 54% 2026-11-19 15:58:37 Lihat Site
SITE00126
Tolinggula Pantai
GORONTALO HUB 53% 2026-11-25 10:51:01 Lihat Site
SITE00123
Bulontiyo barat
GORONTALO PENYANGGA 53% 2026-11-25 10:49:44 Lihat Site
SITE00148
Tete B
SULAWESI TENGAH PENYANGGA 53% 2026-11-24 11:10:42 Lihat Site
SITE00143
Bangko
SULAWESI TENGGARA HUB 53% 2026-10-30 15:14:05 Lihat Site