← Kembali ke Peta

DETAIL PROGRESS KNMP

100
Lokasi Progress Bergerak
41.55%
Progress Nasional
0.37%
Rata-rata per Site
0
Site Selesai 100%
TREND PROGRESS NASIONAL
TOP KENAIKAN PROGRESS
Mattiro Bombang SULAWESI SELATAN
+79%
Lero Pinrang SULAWESI SELATAN
+75%
Limbua SULAWESI BARAT
+70%
Tadang Palie SULAWESI SELATAN
+69%
Punagaya SULAWESI SELATAN
+69%
Terapung SULAWESI TENGGARA
+68%
Tamarupa SULAWESI SELATAN
+67%
Lumpue SULAWESI SELATAN
+66%
Bontorannu SULAWESI SELATAN
+65%
Takkalasi SULAWESI SELATAN
+65%
Data SULAWESI SELATAN
+70%
Arungkeke Pallantikang SULAWESI SELATAN
+64%
Watolo SULAWESI TENGGARA
+65%
Bungeng SULAWESI SELATAN
+63%
Lasama SULAWESI TENGGARA
+63%
RANKING PROVINSI
Provinsi Total Site Avg Completion Hub Penyangga
SULAWESI TENGGARA 15 52.33% 4 11
SULAWESI SELATAN 50 50.54% 7 43
SULAWESI BARAT 6 45.33% 0 6
SULAWESI TENGAH 14 44.50% 2 12
GORONTALO 11 36.09% 1 10
SULAWESI UTARA 15 0.53% 3 12
TOP 10 PROVINSI
ProvinsiAvg Completion
SULAWESI TENGGARA 52.33%
SULAWESI SELATAN 50.54%
SULAWESI BARAT 45.33%
SULAWESI TENGAH 44.50%
GORONTALO 36.09%
SULAWESI UTARA 0.53%
DISTRIBUSI PROGRESS NASIONAL
0%
11
1-25%
12
26-50%
42
51-75%
45
76-99%
1
100%
0
PROGRESS TERBARU
Limbua
SULAWESI BARAT

70% Pekerjaan Kios Perbekalan
pek.plesteran kios perbekalan
2026-11-18 19:40:00
Binanga Karaeng
SULAWESI SELATAN

46% Pekerjaan Kios Perbekalan, Pabrik Es Portable, Shelter Pendaratan Ikan dan Tambatan Perahu
* Pek. Plesteran dinding bangunan kios perbekalan * Pek. Pemasangan dinding bata merah kuda" beton bangunan shelter pendaratan ikan * Pek. Pembesian besi plat lantai bangunan pabrik es portable * Pek. Pemasangan bekisting ringbalk atas dan balok anak tambatan perahu * Pek. Pemasangan batu bela saluran drainase * Fabrikasi pembesian
2026-11-18 19:26:00
Data
SULAWESI SELATAN

70% Pekerjaan Shelter Pendaratan Ikan
* Pek. Bangunan shelter pendaratan ikan * Fabrikasi pembesian
2026-11-18 19:23:00
Siddo
SULAWESI SELATAN

37% Pekerjaan Pabrik Es Portable dan Shelter Pendaratan Ikan
* Pemasangan Bekisting Kolom Bangunan Pabrik Es Portabel * Pengecoran Kolom Bangunan Pabrik Es Portabel * Pemasangan Tapak Precast Bangunan Shelter Pendaratan Ikan
2026-11-18 18:59:00
Munte
SULAWESI SELATAN

42% Pekerjaan DPT dan Urugan Tanah

2026-11-18 18:53:00
Burau Pantai
SULAWESI SELATAN

60% Pekerjaan Shelter Pendaratan Ikan, Kios Perbekalan dan Revetment
* Pemasangan mal balok gantung shelter pendaratan ikan * Persiapan pengecoran rangka beton atap kios perbekalan * Finising tangga revetment
2026-11-18 18:51:00
Bababulo
SULAWESI BARAT

47% Pekerjaan Pabrik Es Portable
•Pek.pembesian pabrik es •pek.pasangan bekisting pabrik es •pek.pengecoran sloof pabrik es
2026-11-18 18:38:00
Bonde Utara
SULAWESI BARAT

34% Pekerjaan DPT
•pek.pembesian dinding DPT •pek.pasangan bekisting dinding DPT
2026-11-18 18:34:00
Takkalala
SULAWESI SELATAN

46% Pekerjaan Tambatan Perahu dan DPT
•pek.pembesian kolom tambatan perahu •pengecoran dpt
2026-11-18 17:48:00
Padang Kalua
SULAWESI SELATAN

52% Pekerjaan Pabrik Es Portable
pek.pengecoran kolom bawah pabrik es
2026-11-18 17:46:00
DETAIL SITE
Site Provinsi Status Completion Updated
SITE00158
Tasiwalie
SULAWESI SELATAN PENYANGGA 38% 2026-11-25 12:01:45 Lihat Site
SITE00028
To'bia
SULAWESI SELATAN PENYANGGA 38% 2026-11-17 11:35:51 Lihat Site
SITE00064
Lampenai
SULAWESI SELATAN PENYANGGA 38% 2026-11-19 15:59:34 Lihat Site
SITE00150
Siddo
SULAWESI SELATAN PENYANGGA 37% 2026-11-19 10:00:06 Lihat Site
SITE00036
Cimpu Utara
SULAWESI SELATAN PENYANGGA 37% 2026-11-16 09:44:31 Lihat Site
SITE00011
Tubo Poang
SULAWESI BARAT PENYANGGA 35% 2026-11-24 10:44:13 Lihat Site
SITE00076
Boyantongo
SULAWESI TENGAH HUB 35% 2026-11-25 09:40:53 Lihat Site
SITE00008
Bonde Utara
SULAWESI BARAT PENYANGGA 34% 2026-11-19 09:35:50 Lihat Site
SITE00020
Songka
SULAWESI SELATAN PENYANGGA 33% 2026-11-24 09:55:51 Lihat Site
SITE00140
Tanjung Bunga
SULAWESI TENGGARA PENYANGGA 33% 2026-11-25 10:06:03 Lihat Site