← Kembali ke Peta

DETAIL PROGRESS KNMP

90
Lokasi Progress Bergerak
18.11%
Progress Nasional
0.19%
Rata-rata per Site
0
Site Selesai 100%
TREND PROGRESS NASIONAL
TOP KENAIKAN PROGRESS
Takkalasi SULAWESI SELATAN
+50%
Mattiro Bombang SULAWESI SELATAN
+46%
Tamarupa SULAWESI SELATAN
+44%
Pajjukukang SULAWESI SELATAN
+43%
Borimasunggu SULAWESI SELATAN
+42%
Lasama SULAWESI TENGGARA
+39%
Bassiang Timur SULAWESI SELATAN
+39%
Latawe SULAWESI TENGGARA
+38%
Lero Pinrang SULAWESI SELATAN
+36%
Bone Pute SULAWESI SELATAN
+36%
Tadang Palie SULAWESI SELATAN
+33%
Karang-karangan SULAWESI SELATAN
+32%
Lakara SULAWESI TENGGARA
+32%
Tanjung Laimeo SULAWESI TENGGARA
+31%
Tondasi SULAWESI TENGGARA
+31%
RANKING PROVINSI
Provinsi Total Site Avg Completion Hub Penyangga
SULAWESI TENGGARA 15 23.73% 4 11
SULAWESI SELATAN 50 20.26% 7 43
SULAWESI BARAT 6 15.83% 0 6
SULAWESI TENGAH 14 15.36% 2 12
GORONTALO 11 5.45% 1 10
TOP 10 PROVINSI
ProvinsiAvg Completion
SULAWESI TENGGARA 23.73%
SULAWESI SELATAN 20.26%
SULAWESI BARAT 15.83%
SULAWESI TENGAH 15.36%
GORONTALO 5.45%
DISTRIBUSI PROGRESS NASIONAL
0%
11
1-25%
58
26-50%
27
51-75%
0
76-99%
0
100%
0
PROGRESS TERBARU
Songka
SULAWESI SELATAN

3% Leveling Lahan, Pengukuran & Pekerjaan Besi
Leveling Lahan, Pengukuran & Pekerjaan Besi
2026-08-06 10:34:00
Takkalasi
SULAWESI SELATAN

2% Fabrikasi Pembesian
*Fabrikasi Pembesian Note: Untuk Sementara waktu permbersihan area kerja belum bisa di lakukan dikarenakan terkendala pembebasan lahan, dan area yang akan dibangun masih terdapat rumah warga, di rencanakan tanggal 10 Agustus akan dilakukan pembongkaran jika berjalan lancar.
2026-08-06 10:10:00
Tondasi
SULAWESI TENGGARA

5% Penerimaan Material & Pematokan Batas Area
* Penerimaan Pasir * Penerimaan Batu Gunung * Pemagaran Area Kerja
2026-08-06 09:44:00
Tirowali
SULAWESI SELATAN

9% Pematokan Untuk Galian Pondasi

2026-08-06 09:02:00
Boyantongo
SULAWESI TENGAH

1% Pemagaran & Mobilisasi Material
Pemagaran & Mobilisasi Material
2026-08-05 16:42:00
Tondasi
SULAWESI TENGGARA

1% Pekerjaan Persiapan
Pekerjaan Persiapan
2026-08-05 12:39:00
Pallameang
SULAWESI SELATAN

6% Perakitan besi dan Pekerjaan Galian
* Pek. Perakitan besi * Pek. Galian Dpt dan Saluran
2026-08-05 11:45:00
Lero Pinrang
SULAWESI SELATAN

9% Pekerjaan Pembangunan Kios Perbekalan
* Pek. Perakitan Besi * Pemasangan Pondasi batu kali kios perbekalan * Fabrikasi Pembesian
2026-08-05 11:37:00
Munte
SULAWESI SELATAN

1% Survey Lokasi
Survey Lokasi Desa Munte
2026-08-05 11:24:00
Tirowali
SULAWESI SELATAN

7% Penimbunan Tanah dan Fabrikasi Besi
* Pekerjaan Pembesian * Pekerjaan Penimbunan(Leveling lahan)
2026-08-05 11:20:00
DETAIL SITE
Site Provinsi Status Completion Updated
SITE00013
Takkalasi
SULAWESI SELATAN PENYANGGA 50% 2026-09-24 10:23:22 Lihat Site
SITE00081
Mattiro Bombang
SULAWESI SELATAN PENYANGGA 46% 2026-09-22 08:30:08 Lihat Site
SITE00101
Tamarupa
SULAWESI SELATAN PENYANGGA 44% 2026-09-23 09:19:15 Lihat Site
SITE00075
Pajjukukang
SULAWESI SELATAN PENYANGGA 43% 2026-09-23 13:40:58 Lihat Site
SITE00078
Borimasunggu
SULAWESI SELATAN PENYANGGA 42% 2026-09-23 11:22:25 Lihat Site
SITE00026
Lasama
SULAWESI TENGGARA PENYANGGA 39% 2026-09-21 17:07:28 Lihat Site
SITE00029
Bassiang Timur
SULAWESI SELATAN PENYANGGA 39% 2026-09-22 08:40:08 Lihat Site
SITE00034
Latawe
SULAWESI TENGGARA PENYANGGA 38% 2026-09-21 17:08:39 Lihat Site
SITE00096
Lero Pinrang
SULAWESI SELATAN HUB 36% 2026-09-23 11:57:19 Lihat Site
SITE00033
Bone Pute
SULAWESI SELATAN PENYANGGA 36% 2026-09-24 13:43:28 Lihat Site