← Kembali ke Peta

DETAIL PROGRESS KNMP

90
Lokasi Progress Bergerak
18.11%
Progress Nasional
0.19%
Rata-rata per Site
0
Site Selesai 100%
TREND PROGRESS NASIONAL
TOP KENAIKAN PROGRESS
Takkalasi SULAWESI SELATAN
+50%
Mattiro Bombang SULAWESI SELATAN
+46%
Tamarupa SULAWESI SELATAN
+44%
Pajjukukang SULAWESI SELATAN
+43%
Borimasunggu SULAWESI SELATAN
+42%
Bassiang Timur SULAWESI SELATAN
+39%
Lasama SULAWESI TENGGARA
+39%
Latawe SULAWESI TENGGARA
+38%
Bone Pute SULAWESI SELATAN
+36%
Lero Pinrang SULAWESI SELATAN
+36%
Tadang Palie SULAWESI SELATAN
+33%
Lakara SULAWESI TENGGARA
+32%
Karang-karangan SULAWESI SELATAN
+32%
Tondasi SULAWESI TENGGARA
+31%
Tanjung Laimeo SULAWESI TENGGARA
+31%
RANKING PROVINSI
Provinsi Total Site Avg Completion Hub Penyangga
SULAWESI TENGGARA 15 23.73% 4 11
SULAWESI SELATAN 50 20.26% 7 43
SULAWESI BARAT 6 15.83% 0 6
SULAWESI TENGAH 14 15.36% 2 12
GORONTALO 11 5.45% 1 10
TOP 10 PROVINSI
ProvinsiAvg Completion
SULAWESI TENGGARA 23.73%
SULAWESI SELATAN 20.26%
SULAWESI BARAT 15.83%
SULAWESI TENGAH 15.36%
GORONTALO 5.45%
DISTRIBUSI PROGRESS NASIONAL
0%
11
1-25%
58
26-50%
27
51-75%
0
76-99%
0
100%
0
PROGRESS TERBARU
Borimasunggu
SULAWESI SELATAN

28% Pemasangan Batu Belah Saluran
Pemasangan Batu Belah Saluran
2026-08-14 09:24:00
Pajjukukang
SULAWESI SELATAN

13% Galian Dinding Penahan Tanah
Galian Dinding Penahan Tanah
2026-08-14 09:21:00
Binanga Karaeng
SULAWESI SELATAN

10% Pekerjaan Bangunan Gudang Beku Portable
* Pek. Perakitan Besi * Pemasangan Pondasi Bangunan Gudang Beku Portable dan Pasangan Batu Kosong * Fabrikasi Pembesian
2026-08-13 19:05:00
Tadang Palie
SULAWESI SELATAN

19% Pekerjaan Pembangunan DPT
* Pek. Perakitan besi * Pekerjaan saluran,Pemasangan Bekisting dan pengecoran Dpt * Fabrikasi Pembesian
2026-08-13 19:00:00
Tirowali
SULAWESI SELATAN

18% Pembangunan Pondasi
* Pemasangan Cerucuk Dolken * Pemasangan Batu Kali untuk Pondasi * Fabrikasi Pembesian
2026-08-13 18:34:00
Belopa
SULAWESI SELATAN

5% Mobilisasi Material & Stakeout
* Penerimaan Material Besi dan Semen * Stakeout Area Lokasi
2026-08-13 17:37:00
Pajjukukang
SULAWESI SELATAN

7% Pemasangan Patok batas, Persiapan Pemasangan Pagar Pembatas Proyek, Instalsi Listrik Kerja dari PLN, Mobilisasi Excavator
Pemasangan Patok batas, Persiapan Pemasangan Pagar Pembatas Proyek, Instalsi Listrik Kerja dari PLN, Mobilisasi Excavator
2026-08-13 16:44:00
Lakara
SULAWESI TENGGARA

12% Penimbunan Lokasi
Uraian Pekerjaan: - Uji Tanah (Sondir) - Pemasangan Pagar Sementara - Penimbunan Lokasi
2026-08-13 16:35:00
Bone Pute
SULAWESI SELATAN

11% Pembuatan kerangka kayu

2026-08-13 16:05:00
Bulete
SULAWESI SELATAN

10% Finishing Direksikeet
Finishing Direksikeet
2026-08-13 16:00:00
DETAIL SITE
Site Provinsi Status Completion Updated
SITE00054
Lakawali Pantai
SULAWESI SELATAN PENYANGGA 21% 2026-09-15 12:52:05 Lihat Site
SITE00059
Wewangriu
SULAWESI SELATAN HUB 21% 2026-09-24 10:15:38 Lihat Site
SITE00158
Tasiwalie
SULAWESI SELATAN PENYANGGA 20% 2026-09-23 10:41:11 Lihat Site
SITE00028
To'bia
SULAWESI SELATAN PENYANGGA 20% 2026-09-22 08:42:33 Lihat Site
SITE00009
Limbua
SULAWESI BARAT PENYANGGA 20% 2026-09-25 09:23:04 Lihat Site
SITE00157
Data
SULAWESI SELATAN PENYANGGA 19% 2026-09-25 09:28:10 Lihat Site
SITE00061
Bawalipu
SULAWESI SELATAN PENYANGGA 19% 2026-09-23 09:27:32 Lihat Site
SITE00036
Cimpu Utara
SULAWESI SELATAN PENYANGGA 19% 2026-09-06 20:54:35 Lihat Site
SITE00079
Laemanta Utara
SULAWESI TENGAH PENYANGGA 19% 2026-09-23 09:15:37 Lihat Site
SITE00138
Muara Sampara
SULAWESI TENGGARA PENYANGGA 18% 2026-09-15 09:49:46 Lihat Site