← Kembali ke Peta

DETAIL PROGRESS KNMP

100
Lokasi Progress Bergerak
41.55%
Progress Nasional
0.37%
Rata-rata per Site
0
Site Selesai 100%
TREND PROGRESS NASIONAL
TOP KENAIKAN PROGRESS
Mattiro Bombang SULAWESI SELATAN
+79%
Lero Pinrang SULAWESI SELATAN
+75%
Limbua SULAWESI BARAT
+70%
Tadang Palie SULAWESI SELATAN
+69%
Punagaya SULAWESI SELATAN
+69%
Terapung SULAWESI TENGGARA
+68%
Tamarupa SULAWESI SELATAN
+67%
Lumpue SULAWESI SELATAN
+66%
Bontorannu SULAWESI SELATAN
+65%
Data SULAWESI SELATAN
+70%
Arungkeke Pallantikang SULAWESI SELATAN
+64%
Watolo SULAWESI TENGGARA
+65%
Takkalasi SULAWESI SELATAN
+65%
Bungeng SULAWESI SELATAN
+63%
Lasama SULAWESI TENGGARA
+63%
RANKING PROVINSI
Provinsi Total Site Avg Completion Hub Penyangga
SULAWESI TENGGARA 15 52.33% 4 11
SULAWESI SELATAN 50 50.54% 7 43
SULAWESI BARAT 6 45.33% 0 6
SULAWESI TENGAH 14 44.50% 2 12
GORONTALO 11 36.09% 1 10
SULAWESI UTARA 15 0.53% 3 12
TOP 10 PROVINSI
ProvinsiAvg Completion
SULAWESI TENGGARA 52.33%
SULAWESI SELATAN 50.54%
SULAWESI BARAT 45.33%
SULAWESI TENGAH 44.50%
GORONTALO 36.09%
SULAWESI UTARA 0.53%
DISTRIBUSI PROGRESS NASIONAL
0%
11
1-25%
12
26-50%
42
51-75%
45
76-99%
1
100%
0
PROGRESS TERBARU
Lero Pinrang
SULAWESI SELATAN

48% Pekerjaan Tambatan Perahu, Bangunan Genset, Saluran dan Shelter Pendaratan Ikan
* Pek. Pengecoran ringbalk/RB-1 atas dan balok anak pada tambatan perahu * Pek. Plesteran dinding pada bangunan genset * Pek. Plesteran saluran drainase dan pemasangan batu bela * Pek. Perakitan dan pemasangan bekisting ringbalk pada bangunan shelter pendaratan ikan * Pek. Bangunan docking kapal * Pek. Acian pada bangunan tangki air * Pek . Pembesian besi plat duiker
2026-10-27 20:06:00
Tasiwalie
SULAWESI SELATAN

28% Pekerjaan Tambatan Perahu, Revetment
* Pek. Perakitan dan pemasangan bekisting ringbalk/RB-1 pada tambatan perahu * Pek. Pembesian besi tangga revetment * Fabrikasi pembesian
2026-10-27 19:52:00
Bababulo
SULAWESI BARAT

36% Pekerjaan DPT dan Saluran
• Pek. pengecoran dinding DPT • Pek. pasangan batu saluran
2026-10-27 19:44:00
Limbua
SULAWESI BARAT

38% Pekerjaan Shelter Pendaratan Ikan dan Pabrik Es Portable
* pek.bekisting,shelter pendaratan ikan * pek.pembesian pabrik es
2026-10-27 19:42:00
Mabonta
SULAWESI SELATAN

40% Pekerjaan Revetment
* Pemasangan bekesting * Pemasangan mal tangga revetment
2026-10-27 19:20:00
Polewali
SULAWESI TENGGARA

29% Pekerjaan Footplate
= pek. Pengecoran footplate = pek. Galian footplate
2026-10-27 19:18:00
Muara Tinobu
SULAWESI TENGGARA

21% Pekerjaan DPT
= pekerjaan pengecoran tapak Dinding Penahan Tanah
2026-10-27 19:10:00
Waetuoe
SULAWESI SELATAN

36% Pekerjaan DPT dan Revetment
* Pek. Pengecoran Tapak dinding penahan tanah * Pek. Pemasangan bekisting dinding penahan tanah revetment * Fabrikasi pembesian
2026-10-27 18:49:00
Limbua
SULAWESI BARAT

38% Pekerjaan Pondasi
Pekerjaan Pengecoran Sloof Pekerjaan Pemadatan Tanah
2026-10-27 18:24:00
Tete B
SULAWESI TENGAH

34% pek pengecoran
Mengikuti perhitungan CCO
2026-10-27 11:27:00
DETAIL SITE
Site Provinsi Status Completion Updated
SITE00060
Harapan
SULAWESI SELATAN PENYANGGA 55% 2026-11-24 09:42:01 Lihat Site
SITE00052
Polewali
SULAWESI TENGGARA HUB 55% 2026-11-25 10:01:29 Lihat Site
SITE00031
Tondasi
SULAWESI TENGGARA PENYANGGA 55% 2026-11-12 10:35:19 Lihat Site
SITE00079
Laemanta Utara
SULAWESI TENGAH PENYANGGA 55% 2026-11-18 10:18:44 Lihat Site
SITE00156
Rantebelu
SULAWESI SELATAN PENYANGGA 54% 2026-11-24 10:28:43 Lihat Site
SITE00044
Mabonta
SULAWESI SELATAN PENYANGGA 54% 2026-11-19 15:58:37 Lihat Site
SITE00126
Tolinggula Pantai
GORONTALO HUB 53% 2026-11-25 10:51:01 Lihat Site
SITE00123
Bulontiyo barat
GORONTALO PENYANGGA 53% 2026-11-25 10:49:44 Lihat Site
SITE00148
Tete B
SULAWESI TENGAH PENYANGGA 53% 2026-11-24 11:10:42 Lihat Site
SITE00143
Bangko
SULAWESI TENGGARA HUB 53% 2026-10-30 15:14:05 Lihat Site